Primary lining completed at construction site
At the construction site, we recently finished concreting the reinforced concrete beam of the retaining wall, which represents the top of the primary lining of the disposal silo. We carried out the removal of the formwork and thus completed the work on the beam, which means that the construction of the primary lining is complete.
We installed a panel fence on the inner perimeter of the beam to protect against possible falls into the construction pit. We are continuing with the backfilling and strengthening of the outer perimeter of the reinforced concrete beam.