Exceptional work at the LILW disposal facility construction site
This week, as part of the construction of the silo, we started inserting the reinforcement for the first panel of the retaining wall. The armature measures more than 60 meters in length, therefore the installation of such fittings is an extremely demanding process, which requires careful planning and great attention in execution. For installation, we also successfully carried out the concreting of the first and second part of the primary panel of the retaining wall, within which more than 1,400 m3 of concrete was installed.